Hi all,

I’ve got a problem with he task scheduler :

I have a TAS script that launch a TDR report and send it by email.

  • when I run the script manually (from the .tas file) eveything is ok

  • when I want to schedule it I have an error : Missing Root Element on Report_1 when executing the script.

Any idea about it ?

Thanks

To Nico:

Thank you for posting in Toad World.

This issue looks reminiscent of QAT-3035 (https://support.quest.com/toad-data-point/kb/126225). This fix is present in our one-offs! Please download and upgrade to the one-off of Toad Data Point.

Base: http://community-downloads.quest.com/toadsoft/tda/ToadDataPoint_Base_3.5.0.2945.zip

Pro: http://community-downloads.quest.com/toadsoft/tda/ToadDataPoint_pro_3.5.0.2945.zip

Software Associate Developer I,
-Joshua Liong

Hi Joshua,

Thanks for your answer, I’ve installed the upgrade and it’s ok now.